Key facts
Application
Hydropower
Country
Türkiye
Project type
New construction
Design flow
4,424 l/s
Model
ADENCO-127-1
Number of screens
28
Material
304 stainless steel
Lead time
8 weeks (28 screens including two custom widths; CAD modelling and USBR-based hydraulic design)
Commissioned
2021

Overview

During concrete pouring the two side-by-side weirs, each designed at 14 m, were built to the wrong widths: one 200 mm too narrow (13,800 mm) and the other 150 mm too wide (14,150 mm). Rebuilding the concrete was not economically viable.

Instead of changing the concrete, ADENCO adapted the screens to it: 26 screens in standard width plus two custom screens of 150 mm and 800 mm. The 150 mm unit is one of the smallest Coanda screens ever built. Design was carried out with CAD modelling and USBR-based hydraulic analysis.

Because ADENCO designed the intake structure from the outset, water reaches the screens uniformly across the full weir width. The full project was delivered in 8 weeks, and the hydropower plant has been operating at high performance ever since, with zero unplanned cleaning interventions in the commissioning year.

Hydropower plants in Türkiye are approved for operation by Devlet Su İşleri (DSİ), the Turkish State Hydraulic Works. ADENCO prepared and submitted the complete documentation package for the Coanda intake to DSİ: the preliminary approval reports, the acceptance analysis reports and the design reports. All of it was approved, and the intake went into operation on that basis.

Results

4,424 l/sTotal Capacity
28Intake Screens
2Custom Widths

Gallery

The two Gongele weirs seen from the dry riverbed downstream during construction, with the Coanda screen row fitted below the weir crest across the full width
The two weirs during construction, seen from the dry riverbed downstream, with the row of Coanda screens fitted below the weir crest across the full width.
Installed Coanda screens extending along the full length of one Gongele weir, seen along the wedge wire face
Installed Coanda screens along the full length of one weir, seen along the wedge wire face.
The wedge wire face of the installed Gongele screens, with the mounting brackets along the lower edge
The wedge wire face of the installed screens, with the mounting brackets along the lower edge.
Gongele HPP: Antalya: installation photo 1Gongele HPP: Antalya: installation photo 2
Gongele HPP: Antalya: installation photo 3
Gongele HPP: Antalya: installation photo 4
PROJECT DETAILS
LocationAntalya, Türkiye
ApplicationHydropower
ProductADENCO-127-1
Number of screens28
Capacity4,424 l/s
Year2021
TypeNew construction

Delivered with ISO 9001 documentation, EN 10204 3.1 material certificates, and factory and site acceptance test (FAT/SAT) procedures.